Summary print

Preview & Print

Properties

Steps (29) arrow_drop_up arrow_drop_down
Security clearance (local partner)  (2) expand_more expand_less
Legal stamps (local partner)  (1) expand_more expand_less
FDI registration certificate  (2) expand_more expand_less
Company registration  (3) expand_more expand_less
Site layout plan and location map  (1) expand_more expand_less
Land use agreement  (1) expand_more expand_less
Land use approval from gewog  (2) expand_more expand_less
Location clearance  (2) expand_more expand_less
Project approval  (6) expand_more expand_less
Business license  (2) expand_more expand_less
Foreign currency account  (5) expand_more expand_less
Tax payer number  (2) expand_more expand_less
language
language
flag

9
Obtain site layout plan and location map
(last modified: 27/02/2023)

Costs

( see details )

Wait until next step

Free of charge
 -  30 days

Contact details

Entity in charge

Any licensed architect/ engineer or architectural/ engineering firm


Expected results

Site layout plan
Location map

Cost Free

Costs may be applicable and amount may vary depending on the area, size of the project and other factors.

Time frame

This step will take a maximum of 30 days depending on the engineer/ architect
Waiting time until next step: Max.   30 days
Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License