List of steps
(Total number of steps: 10)
Prepare architectural, structural and other drawings copy  (1)
Obtain consent from the gewog administration  (1)
Obtain construction permit  (8)

Preview & Print

Properties
 
Summary of the procedure
 

Where to go? (4)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Any licensed architect/ engineer or architectural/ engineering firm
1
Any licensed architect/ engineer or architectural/ engineering firm
Any Concerned Geog Administration Office
2
Any Concerned Geog Administration Office
District Administration, Thimphu (x 4)
3 4 9 10
District Administration, Thimphu
Bhutan Power Corporation, Electricity Service Division, Thimphu (x 4)
5 6 7 8
Bhutan Power Corporation, Electricity Service Division, Thimphu

What you will get (0)

The objective of the procedure is to obtain those documents.
-

Required documents 

The documents with green band will be provided to you during the procedure.

Letter for power cleareance
5
Letter for power cleareance

How much?

Free of charge

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 9 d 28 d
of which:
Waiting time in queue (sum): 0mn 25mn
Attention at counter: 10mn 55mn
Waiting time until next step (sum): 9 d 28 d

Legal justification?

The regulations which justify the procedure and its content
Bhutan Building Rules 2002 Bhutan Building Rules 2002
  articles 4.2, 4.1, 4.3, 7, 9, 11, 12, 13, Annex 4
Bhutanese Architectural Guidelines 2014 Bhutanese Architectural Guidelines 2014
Rural Construction Rules 2013 Rural Construction Rules 2013
  articles 4, 6
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License