Obtain Security Clearance  (2) expand_more expand_less
Purchase legal stamps  (1) expand_more expand_less
Site layout plan and location map  (1) expand_more expand_less
Obtain gewog administrative approval  (2) expand_more expand_less
Obtain location clearance  (2) expand_more expand_less
Obtain project approval  (7) expand_more expand_less
Business license  (3) expand_more expand_less
Open current bank account  (1) expand_more expand_less
Obtain tax payer number  (2) expand_more expand_less
language
language
flag

4
Obtain site layout plan and location map
(last modified: 27/02/2023)

Costs

( see details )

Wait until next step

Free of charge
 -  30 days

Contact details

Entity in charge

Any licensed architect/ engineer or architectural/ engineering firm


Expected results

Site layout plan
Location map

Cost Free

Costs may be applicable and amount may vary depending on the area, size of the project and other factors.

Time frame

This step will take a maximum of 30 days depending on the engineer/ architect
Waiting time until next step: Max.   30 days