Steps (33) arrow_drop_up arrow_drop_down
Purchase legal stamps  (1) expand_more expand_less
Obtain security clearance  (2) expand_more expand_less
Obtain name clearance  (1) expand_more expand_less
Obtain FDI registration certificate  (2) expand_more expand_less
Obtain business guest visa clearance  (4) expand_more expand_less
Obtain site layout and location maps  (1) expand_more expand_less
Sign agreement on land use  (1) expand_more expand_less
Obtain gewog administrative approval  (2) expand_more expand_less
Obtain location clearance  (2) expand_more expand_less
Register company  (3) expand_more expand_less
Obtain project approval  (5) expand_more expand_less
Obtain business license  (3) expand_more expand_less
Open bank account  (4) expand_more expand_less
Obtain tax payer number  (2) expand_more expand_less
language
flag

11
Obtain site layout and location maps
(last modified: 18/06/2018)

Costs

( see details )

Wait until next step

Free of charge
0 days  -  30 days

Contact details

Entity in charge

Any licensed architect/ engineer or architectural/ engineering firm


Expected results

Site layout plan
Location map

Cost Free

Costs may be applicable and amount may vary depending on area of location, size of the project and other factors.

Time frame

This step will take a maximum of 30 days depending on the engineer/ architect
Waiting time until next step: Max.  30 days
Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License