Steps (18) arrow_drop_up arrow_drop_down
Location map  (1) expand_more expand_less
Architectural, structural and other drawings  (1) expand_more expand_less
Site clearance from Bhutan Power Corporation  (4) expand_more expand_less
Environmental clearance  (3) expand_more expand_less
Official site plan  (4) expand_more expand_less
Construction permit  (5) expand_more expand_less

14
Request construction permit
(last modified: 31/01/2023)

Timeframe ( see details )

Wait until next step

0 mn  -  15 mn
3 days  -  15 days

Contact details

Entity in charge

Thromde, Samdrupjongkhar

Samdrupjongkhar
Tel: +975 7 251 616 / +975 7 251 619
Fax: +975 7 251 305
Email: webmaster@sjthromde.gov.bt
Website: http://www.sjthromde.gov.bt/node/1

Unit in charge

Compliance & Enforcement Division, Samdrupjongkhar Thromde

Mon: 09:00 - 01:00, 02:00 - 05:00
Tue: 09:00 - 01:00, 02:00 - 05:00
Wed: 09:00 - 01:00, 02:00 - 05:00
Thu: 09:00 - 01:00, 02:00 - 05:00
Fri: 09:00 - 01:00, 02:00 - 05:00
Sat: closed
Sun: closed

Person in charge

Dorji Wangdi

Urban Planner
Tel: +975 17 618 125
Email: dwangdi@sjthromde.gov.bt

Expected results

Appointment

Requirements

1. Building application form
Building application form (original)
2. 01 - Libre deuda de patente
Official site plan (original)
3. 01 - Libre deuda de patente
Architectural drawings (3 simple copies)
3 sets clearly identifying the designer
4. 01 - Libre deuda de patente
Structural drawings (3 simple copies)
3 sets clearly identifying the designer
5. 01 - Libre deuda de patente
Sanitary/ sewerage drawing (3 simple copies)
6. 01 - Libre deuda de patente
Plumbing/ water supply drawings (3 simple copies)
7. 01 - Libre deuda de patente
Electrical/ telephone connection drawings (3 simple copies)
8. 01 - Libre deuda de patente
Site clearance from BPC (Simple copy)
9. 01 - Libre deuda de patente
Passport size photograph of business guest (original)
to be attached on the application form
10. 01 - Libre deuda de patente
Latest land/ property ownership certificate (Simple copy)
required if the construction is on private land
11. 01 - Libre deuda de patente
Certificates of architect and design engineers (Simple copy)
1 copy each
12. 01 - Libre deuda de patente
Registration number of Architect issued by Construction Development Board (Simple copy)
13. 01 - Libre deuda de patente
Authorization letter for construction permit (original)
if the applicant is not the legal owner of the property

Time frame

Waiting time in queue: Max.  5mn
Attention at counter: Max.   10mn
Waiting time until next step: Min.   3 days - Max.   15 days

Legal justification

1. Bhutan Building Rules 2018
Bhutan Building Rules 2018
Sections 4.1, 4.2
2. Development Control Regulations-2004
Development Control Regulations-2004
Section 2A ,  Article icle2.0

Additional information

Once the drawings submitted are approved, Development Regulatory Division will notify the proponent to accompany the team for a site visit.

Recourse: Thromde, Samdrupjongkhar

Entity in charge

Thromde, Samdrupjongkhar

Samdrupjongkhar
Tel: +975 7 251 616 / +975 7 251 619
Fax: +975 7 251 305
Email: webmaster@sjthromde.gov.bt
Website: http://www.sjthromde.gov.bt/node/1

Unit in charge

Compliance & Enforcement Division, Samdrupjongkhar Thromde

Mon: 09:00 - 01:00, 02:00 - 05:00
Tue: 09:00 - 01:00, 02:00 - 05:00
Wed: 09:00 - 01:00, 02:00 - 05:00
Thu: 09:00 - 01:00, 02:00 - 05:00
Fri: 09:00 - 01:00, 02:00 - 05:00
Sat: closed
Sun: closed

Person in charge

Sangay Jamtsho

Development Regulatory Head
Tel: +975 17 887 154
Email: sjamtsho@sjthromde.gov.bt